[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1160167,821,1,"单选题","施工项目经理检查施工进度时，发现施工进度滞后是由于其自身材料采购的原因造成的，则为纠正进度偏差可以采取的组织措施是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整采购部门管理人员",true,{"key":16,"text":17,"correct":18},"B","调整材料采购价格",false,{"key":20,"text":21,"correct":18},"C","增加材料采购的资金投人",{"key":23,"text":24,"correct":18},"D","变更材料采购合同","施工项目经理检查施工进度时，发现施工进度滞后是由于其自身材料采购的原因造成的，则为纠正进度偏差可以采取的组织措施是调整采购部门管理人员。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]