[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160158,821,1,"单选题","在双代号时标网络计划中，关键路线是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","没有虚工作的线路",false,{"key":16,"text":17,"correct":18},"B","关键结点组成的线路",true,{"key":20,"text":21,"correct":14},"C","没有波形线的线路",{"key":23,"text":24,"correct":14},"D","持续时间最长工作所在的线路","在双代号时标网路计划中，凡自始至终不出现波形线的线路即为关键线路。因为不出现波形线，就说明在这条线路上相邻两项工作之间的时间间隔全部为零，也就是在计算工期等于计划工期的前提下，这些工作的总时差和自由时差全部为零。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]