[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1160154,821,1,"单选题","已知在双代号网络计划中，某工作有四项紧后工作，它们的最迟开始时间分别为第16天、第17天、第19天和第20天。如果该工作的持续时间为6天，则其最迟开始时间为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10天",true,{"key":16,"text":17,"correct":18},"B","11天",false,{"key":20,"text":21,"correct":18},"C","12天",{"key":23,"text":24,"correct":18},"D","14天","已知在双代号网络计划中，某工作有四项紧后工作，它们的最迟开始时间分别为第16天、第17天、第19天和第20天。如果该工作的持续时间为6天，则其最迟开始时间为16-6=10天。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]