[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160153,821,1,"单选题","（ ）是把施工对象划分成若干施工段，每个施工过程的专业队（组）依次连续地在每个施工段上进行作业，不同的施工过程，按照工程对象的施工工艺要求，先后相继投人施工，使各专业队（组）在不同的空间范围内可以互不干扰地同时进行不同的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平行施工",false,{"key":16,"text":17,"correct":18},"B","流水施工",true,{"key":20,"text":21,"correct":14},"C","依次施工",{"key":23,"text":24,"correct":14},"D","重复施工","流水施工是把施工对象划分成若干施工段，每个施工过程的专业队（组）依次连续地在每个施工段上进行作业，不同的施工过程，按照工程对象的施工工艺要求，先后相继投人施工，使各专业队（组）在不同的空间范围内可以互不干扰地同时进行不同的工作。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]