[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160148,821,1,"单选题","某工程网络计划中，已知工作M的总时差和自由时差分别为7天和4天，监理工程师检查实际进度时，发现该工作的持续时间延长了5天，说明此时工作M的实际进度将其紧后工作的最早开始时间推迟了（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5天，但不影响总工期",false,{"key":16,"text":17,"correct":18},"B","1天，但不影响总工期",true,{"key":20,"text":21,"correct":14},"C","5天，并使总工期延长1天",{"key":23,"text":24,"correct":14},"D","4天，并使总工期延长2天","自由时差为不影响紧后工作最早开始时间的本项工作的自有时间，总时差为不影响总工期的机动时间5-4=1",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]