[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1160146,821,1,"单选题","建设工程项目按施工成本组成编制施工成本计划，是要将施工成本分解为（ ），从而确定相应的分项计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直接费、间接费、利润、税金",false,{"key":16,"text":17,"correct":14},"B","单位工程施工成本及分部、分项施工成本",{"key":19,"text":20,"correct":21},"C","人工费、材料费、施工机械使用费、措施费、间接费",true,{"key":23,"text":24,"correct":14},"D","建筑工程费和安装工程费","建设工程项目按施工成本组成编制施工成本计划，是要将施工成本分解为人工费、材料费、施工机械使用费、措施费、间接费，从而确定相应的分项计划。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]