[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160138,821,1,"单选题","（ ）是指在项目完成后，对项目成本形成中的各责任者，按项目成本目标责任制的有关规定，将成本的实际指标与计划、定额、预算进行对比和考核，评定项目成本计划的完成情况和各责任者的业绩，并以此给以相应的奖励和处罚。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本预测",false,{"key":16,"text":17,"correct":18},"B","成本考核",true,{"key":20,"text":21,"correct":14},"C","成本核算",{"key":23,"text":24,"correct":14},"D","成本控制","成本考核是指在项目完成后，对项目成本形成中的各责任者，按项目成本目标责任制的有关规定，将成本的实际指标与计划、定额、预算进行对比和考核，评定项目成本计划的完成情况和各责任者的业绩，并以此给以相应的奖励和处罚。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]