[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1160135,821,1,"单选题","建立进度控制小组，将进度控制任务落实到个人；建立进度报告制度和进度信息沟通网络是进度控制措施中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","建立进度控制小组，将进度控制任务落实到个人；建立进度报告制度和进度信息沟通网络是进度控制措施中的组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]