[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160131,821,1,"单选题","当网络图中某一非关键工作的持续时间拖延且大于该工作的总时差TF时，网络计划总工期将（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖延δ",false,{"key":16,"text":17,"correct":18},"B","拖延δ—TF",true,{"key":20,"text":21,"correct":14},"C","拖延TF+δ",{"key":23,"text":24,"correct":14},"D","拖延TF-δ","根据总时差的概念，当工作的持续时间拖延，大于总时差时，超出的部分将会影响到总工期。当网络图中某一非关键工作的持续时间拖延且大于该工作的总时差TF时，网络计划总工期将拖延δ—TF。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]