[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160128":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1160128,821,1,"单选题","建设工程项目总进度目标的控制是（ ）项目管理的任务。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工方",false,{"key":16,"text":17,"correct":14},"B","设计方",{"key":19,"text":20,"correct":21},"C","业主方",true,{"key":23,"text":24,"correct":14},"D","供货方","建设工程项目的总进度目标指的是整个项目的进度目标，它是在项目决策阶段项目定义时确定的，项目管理的主要任务是在项目的实施阶段对项目的目标进行控制。建设工程项目总进度目标的控制是业主方项目管理的任务（若采用建设项目总承包的模式，协助业主进行项目总进度目标的控制也是建设项目总承包方项目管理的任务）。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]