[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1160126,821,1,"单选题","项目动态控制的准备工作是将已找出的项目目标进行分解，以确定用于目标控制的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","偏差值",false,{"key":16,"text":17,"correct":14},"B","调整值",{"key":19,"text":20,"correct":21},"C","计划值",true,{"key":23,"text":24,"correct":14},"D","实际值","在项目目标动态控制工作程序中，项目目标动态控制的准备工作是将项目的目标进行分解，以确定用于目标控制的计划值。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]