[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160124,821,1,"单选题","在组织流水施工时，划分的流水施工参数中，流水段属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工艺参数",false,{"key":16,"text":17,"correct":18},"B","空间参数",true,{"key":20,"text":21,"correct":14},"C","时间参数",{"key":23,"text":24,"correct":14},"D","平面参数","流水施工参数一般分为工艺参数、空间参数和时间参数三类。工艺参数包括施工过程和流水强度；空间参数包括工作面、流水施工段和施工层；时间参数包括流水节拍和流水步距。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]