[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1160123,821,1,"单选题","（ ）是指在施工过程中，对影响项目成本的各种因素加强管理，并采取各种有效措施，将施工中实际发生的各种消耗和支出严格控制在成本计划范围内，随时揭示并及时反馈，计算实际成本和计划成本之间的差异并进行分析，消除施工中的损失浪费现象，发现和总结先进经验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本预测",false,{"key":16,"text":17,"correct":14},"B","成本计划",{"key":19,"text":20,"correct":14},"C","成本核算",{"key":22,"text":23,"correct":24},"D","成本控制",true,"成本控制是指在施工过程中，对影响项目成本的各种因素加强管理，并采取各种有效措施，将施工中实际发生的各种消耗和支出严格控制在成本计划范围内，随时揭示并及时反馈，计算实际成本和计划成本之间的差异并进行分析，消除施工中的损失浪费现象，发现和总结先进经验。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]