[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1160096,821,1,"单选题","框架结构模板的拆除顺序一般是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","柱→楼板→梁侧板→梁底板",true,{"key":16,"text":17,"correct":18},"B","梁侧板→梁底板→楼板→柱",false,{"key":20,"text":21,"correct":18},"C","柱→梁侧板→梁底板→楼板",{"key":23,"text":24,"correct":18},"D","梁底板→梁侧板→楼板→柱","框架结构模板的拆除顺序一般是柱→楼板→梁侧板→梁底板。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]