[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1160058,821,1,"单选题","浅基础施工程序正确的是：（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","定位放线→产验槽→开挖土方→浇垫层→立模、扎钢筋→浇混冱土、养护→回填",false,{"key":16,"text":17,"correct":14},"B","定位放线→浇垫层→开挖土方→验槽→浇混凝、养护→立模、扎钢筋→回填",{"key":19,"text":20,"correct":14},"C","定位放线→开挖土方→验槽→立模、扎钢筋→浇垫层→浇混凝土、养护→回填",{"key":22,"text":23,"correct":24},"D","定位放线→开挖土方→验槽→浇垫层→立模、扎钢筋→浇混凝土、养护→回填",true,"浅基础施工程序是定位放线→开挖土方→验槽→浇垫层→立模、扎钢筋→浇混凝土、养护→回填。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]