[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160044,821,1,"单选题","下列关于掺防水剂水泥砂浆防水施工的说法中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工工艺流程为：找平层施工→防水层施工→质量检查",false,{"key":16,"text":17,"correct":18},"B","当施工采用抹压法时，先在基层涂刷一层1:0.4的水泥浆，随后分层铺抹防水砂浆，每层厚度为10～15mm，总厚度不小于30mm",true,{"key":20,"text":21,"correct":14},"C","氯化铁防水砂浆施工时，底层防水砂浆抹完12h后，抹压面层防水砂浆，其厚13mm分两遍抹压",{"key":23,"text":24,"correct":14},"D","防水层施工时的环境温度为5～35℃","掺防水剂水泥砂浆防水施工的施工工艺流程为：找平层施工→防水层施工→质量检查。防水层施工时的环境温度为5～35℃。当施工采用抹压法时，先在基层涂刷一层1:0.4的水泥浆，随后分层铺抹防水砂浆，每层厚度为5～10mm，总厚度不小于20mm。氯化铁防水砂浆施工时，底层防水砂浆抹完12h后，抹压面层防水砂浆，其厚13mm分两遍抹压。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]