[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1160030,821,1,"单选题","模板拆除顺序应按设计方案进行。当无规定时，应按按照（ ）顺序拆除混凝土模板。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先支后拆，后支先拆",true,{"key":16,"text":17,"correct":18},"B","先支先拆，后支后拆",false,{"key":20,"text":21,"correct":18},"C","先拆承重模板，后拆非承重模板",{"key":23,"text":24,"correct":18},"D","先拆复杂部分，后拆简单部分","模板拆除顺序应按设计方案进行。当无规定时，应按按照先支后拆，后支先拆顺序拆除混凝土模板。因为一般先支的是承重部分，后支的是非承重部分，为了安全起见，应这样操作。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]