[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1159616":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1159616,820,2,"多选题","施工准备阶段的质量控制主要包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","图纸会审和技术交底",true,{"key":16,"text":17,"correct":14},"B","施工组织设计的审查",{"key":19,"text":20,"correct":14},"C","开工申请审查",{"key":22,"text":23,"correct":14},"D","施工生产要素配置质量审查",{"key":25,"text":26,"correct":27},"E","隐蔽工程质量检查",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"通用基础","建筑工程",0]