[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1159615":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1159615,820,2,"多选题","施工阶段的质量控制主要包括(.)。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","作业技术交底",true,{"key":16,"text":17,"correct":14},"B","施工过程质量控制",{"key":19,"text":20,"correct":14},"C","工程变更审查",{"key":22,"text":23,"correct":24},"D","施工生产要素配置质量审查",false,{"key":26,"text":27,"correct":14},"E","隐蔽工程质量检查","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"通用基础","建筑工程",0]