[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158624":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1158624,818,3,"判断题","根据《砌体结构工程施工质量验收规范》GB50203-2011，砖砌体施工时，砌筑混凝土多孔砖、混凝土实心砖时，砖应提前1~2天浇水湿润。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"根据《砌体结构工程施工质量验收规范》GB50203-2011，砖砌体施工时，砌筑混凝土多孔砖及混凝土实心砖不需浇水湿润。",{"id":6,"name":21,"category":22,"favorite":23},"(标准员)专业管理实务 岗位知识","建筑工程",0]