[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158613":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1158613,818,3,"判断题","根据《混凝土结构工程施工规范》GB50666-2011，混凝土结构工程施工时，对模板及支架，应进行设计。模板及支架应具有足够的承载力、刚度、稳定性，应能可靠地承受施工过程中所产生的各类荷载。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(标准员)专业管理实务 岗位知识","建筑工程",0]