[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158437":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158437,818,2,"多选题","施工单位根据专家组的论证报告，对高大模板支撑系统专项施工方案进行修改完善，并经（ ）批准签字后，方可组织实施。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工单位技术负责人",true,{"key":16,"text":17,"correct":14},"B","项目总监理工程师",{"key":19,"text":20,"correct":21},"C","施工单位项目负责人",false,{"key":23,"text":24,"correct":21},"D","安全监督管理部门相关人员",{"key":26,"text":27,"correct":14},"E","建设单位项目负责人","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]