[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158388":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158388,818,2,"多选题","预应力分项工程施工质量验收的一般要求有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","后张法预应力工程的施工应由具有相应资质等级的预应力专业施工单位承担",true,{"key":16,"text":17,"correct":18},"B","先张法预应力工程的施工应由具有相应资质等级的预应力专业施工单位承担",false,{"key":20,"text":21,"correct":14},"C","预应力筋张拉机具设备及仪表，应定期维护和校验",{"key":23,"text":24,"correct":14},"D","在浇筑混凝土之前，应进行预应力隐蔽工程验收",{"key":26,"text":27,"correct":18},"E","浇筑完混凝土时，应进行蒸汽养护","ACD","预应力分项工程施工质量验收的一般要求：①后张法预应力工程的施工应由具有相应资质等级的预应力专业施工单位承担；②预应力筋张拉机具设备及仪表，应定期维护和校验；③在浇筑混凝土之前，应进行预应力隐蔽工程验收。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]