[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158348":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158348,818,2,"多选题","根据《施工现场临时用电安全技术规范》JGJ46-2005，电缆线路应采用（ ），并应避免机械损伤和介质腐蚀。埋地电缆路径应设方位标志。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","埋地敷设",true,{"key":16,"text":17,"correct":14},"B","架空敷设",{"key":19,"text":20,"correct":21},"C","套管敷设",false,{"key":23,"text":24,"correct":21},"D","沿地面明设",{"key":26,"text":27,"correct":21},"E","埋砂敷设","AB","根据《施工现场临时用电安全技术规范》JGJ46-2005，电缆线路应采用埋地敷设和架空敷设，并应避免机械损伤和介质腐蚀。埋地电缆路径应设方位标志。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]