[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158333":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158333,818,2,"多选题","根据《建筑施工塔式起重机安装、使用、拆卸安全技术规程》JGJ196-2010，塔式起重机在安装前和使用过程中，发现有（ ）安全装置不齐全或失效的情况之一的，不得安装和使用。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","结构件上有可见裂纹和严重锈蚀的",true,{"key":16,"text":17,"correct":14},"B","主要受力构件存在塑性变形的",{"key":19,"text":20,"correct":14},"C","钢丝绳达到报废标准的",{"key":22,"text":23,"correct":14},"D","连接件存在严重磨损和塑性变形的",{"key":25,"text":26,"correct":27},"E","证书不全",false,"ABCD","根据《建筑施工塔式起重机安装、使用、拆卸安全技术规程》JGJ196-2010，塔式起重机在安装前和使用过程中，发现有结构件上有可见裂纹和严重锈蚀的、主要受力构件存在塑性变形的、钢丝绳达到报废标准的、连接件存在严重磨损和塑性变形的、安全装置不齐全或失效的情况之一的，不得安装和使用。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]