[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158327":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158327,818,2,"多选题","根据《建筑工程施工质量验收统一标准》GB50300-2013，主体结构分部工程验收的参加人员包括（ ）和施工单位技术、质量部门负责人。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目经理",true,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":21},"C","业主代表",false,{"key":23,"text":24,"correct":21},"D","勘察单位项目负责人",{"key":26,"text":27,"correct":14},"E","设计单位项目负责人","ABE","根据《建筑工程施工质量验收统一标准》GB50300-2013，主体结构分部工程验收的参加人员包括项目经理、总监理工程师、设计单位项目负责人和施工单位技术、质量部门负责人。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]