[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158324":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158324,818,2,"多选题","根据《施工现场临时用电安全技术规范》JGJ46-2005规定，临时用电工程必须经过（ ）共同验收，合格后方可投入使用。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","使用者",false,{"key":16,"text":17,"correct":18},"B","编制、审核、批准部门",true,{"key":20,"text":21,"correct":18},"C","使用单位",{"key":23,"text":24,"correct":14},"D","监理单位",{"key":26,"text":27,"correct":14},"E","业主","BC","根据《施工现场临时用电安全技术规范》JGJ46-2005规定，临时用电工程必须经过编制、审核、批准部门和使用单位共同验收，合格后方可投入使用。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]