[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158285":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1158285,818,2,"多选题","标准体系涉及面广，对于工程项目标准体系评价结论应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","标准体系是否满足工程建设的需要",true,{"key":16,"text":17,"correct":18},"B","标准体系是否能够覆盖所承建的所有项目",false,{"key":20,"text":21,"correct":18},"C","标准体系构成的所有标准是否能满足国家强制性标准规定",{"key":23,"text":24,"correct":18},"D","标准体系是否满足企业标准体系要求",{"key":26,"text":27,"correct":14},"E","标准体系的整改措施建议","AE","评价的结论应包括标准体系是否满足工程建设的需要和整改措施建议两部分。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)专业管理实务 岗位知识","建筑工程",0]