[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1158205,818,1,"单选题","搭设跨度在（ ）m及以上，施工总荷载在（ ）kN\u002F㎡及以上的混凝土模板支撑工程属于危险性较大的分部分项工程。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5，7",false,{"key":16,"text":17,"correct":14},"B","6，8",{"key":19,"text":20,"correct":14},"C","5，10",{"key":22,"text":23,"correct":24},"D","10，10",true,"属于危险性较大的分部分项工程中的模板及支撑体系包括：（一）各类工具式模板工程：包括大模板、滑模、爬模、飞模等工程。（二）混凝土模板支撑工程：搭设高度5m及以上；搭设跨度10m及以上；施工总荷载10kN\u002Fm2及以上；集中线荷载15kN\u002Fm2及以上；高度大于支撑水平投影宽度且相对独立无联系构件的混凝土模板支撑工程。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]