[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1158157,818,1,"单选题","填充墙砌体工程中，填充墙砌至接近梁、板底时，应留一定空隙，等填充墙砌筑完并至少间隔（ ）天后，再将其补砌挤紧。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","15","填充墙砌体工程中，填充墙砌至接近梁、板底时，应留一定空隙，等填充墙砌筑完并至少间隔14天后，再将其补砌挤紧。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]