[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1158151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1158151,818,1,"单选题","分部工程应由（ ）组织施工单位项目负责人和技术、质量负责人等进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位项目技术负责人",false,{"key":16,"text":17,"correct":18},"B","建设单位项目负责人",true,{"key":20,"text":21,"correct":14},"C","施工单位项目技术负责人",{"key":23,"text":24,"correct":14},"D","施工单位项目负责人","分部工程应由总监理工程师（建设单位项目负责人）组织施工单位项目负责人和技术、质量负责人等进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]