[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1157991,818,1,"单选题","根据《大体积混凝土施工规范》GB50496-2009，冬期浇筑大体积混凝土时，冬期浇筑混凝土，宜采用热水拌合、加热骨料等提高混凝土原材料温度的措施，混凝土人模温度不宜低于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","-5℃",false,{"key":16,"text":17,"correct":14},"B","0℃",{"key":19,"text":20,"correct":14},"C","3℃",{"key":22,"text":23,"correct":24},"D","5℃",true,"根据《大体积混凝土施工规范》GB50496-2009，冬期浇筑大体积混凝土时，冬期浇筑混凝土，宜采用热水拌合、加热骨料等提高混凝土原材料温度的措施，混凝土人模温度不宜低于5℃。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]