[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1157958,818,1,"单选题","根据《建筑工程施工质量验收统一标准》GB50300-2013，单位工程完工后，施工单位应组织有关人员进行自检。总监理工程师应组织各专业监理工程师对工程质量进行竣工预验收。存在施工质量问题时，应由施工单位整改。整改完毕后，由（ ）向建设单位提交工程竣工报告，申请工程竣工验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","施工单位",true,{"key":23,"text":24,"correct":14},"D","勘察单位项目负责人","根据《建筑工程施工质量验收统一标准》GB50300-2013，单位工程完工后，施工单位应组织有关人员进行自检。总监理工程师应组织各专业监理工程师对工程质量进行竣工预验收。存在施工质量问题时，应由施工单位整改。整改完毕后，由施工单位向建设单位提交工程竣工报告，申请工程竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]