[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1157955,818,1,"单选题","根据《大体积混凝土施工规范》CJB50496-2009，炎热天气浇筑大体积混凝土时，宜采用遮盖、洒水、拌冰屑等降低混凝土原材料温度的措施，混凝土人模温度宜控制在（ ）以下。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30℃",true,{"key":16,"text":17,"correct":18},"B","25℃",false,{"key":20,"text":21,"correct":18},"C","35℃",{"key":23,"text":24,"correct":18},"D","20℃","根据《大体积混凝土施工规范》CJB50496-2009，炎热天气浇筑大体积混凝土时，宜采用遮盖、洒水、拌冰屑等降低混凝土原材料温度的措施，混凝土人模温度宜控制在30℃以下。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]