[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1157951,818,1,"单选题","根据《建筑工程施工质量验收统一标准》GB50300-2013，分部工程应由（ ）组织施工单位项目负责人和项目技术负责人等进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","专业监理工程师",{"key":23,"text":24,"correct":14},"D","项目技术负责人","根据《建筑工程施工质量验收统一标准》GB50300-2013，分部工程应由总监理工程师组织施工单位项目负责人和项目技术负责人等进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]