[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1157942,818,1,"单选题","根据《混凝土结构工程施工质量验收规范》GB50204-2015，预应力钢筋进场时，应按国家现行标准抽取试件作抗拉强度、（ ）检验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直径偏差",false,{"key":16,"text":17,"correct":14},"B","弯曲性能",{"key":19,"text":20,"correct":14},"C","重量偏差",{"key":22,"text":23,"correct":24},"D","伸长率",true,"根据《混凝土结构工程施工质量验收规范》GB50204-2015，预应力钢筋进场时，应按国家现行标准抽取试件作抗拉强度和伸长率检验。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]