[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157918":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1157918,818,1,"单选题","根据《屋面工程质量验收规范》GB50207-2012，屋面防水工程完工后，应进行观感质量检查和雨后观察或淋水、（ ），不得有渗漏和积水现象。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","放水试验",false,{"key":16,"text":17,"correct":18},"B","蓄水试验",true,{"key":20,"text":21,"correct":14},"C","浇水试验",{"key":23,"text":24,"correct":14},"D","肉眼观察","根据《屋面工程质量验收规范》GB50207-2012，屋面防水工程完工后，应进行观感质量检查和雨后观察或淋水、蓄水试验，不得有渗漏和积水现象。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]