[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1157903,818,1,"单选题","根据《建筑施工塔式起重机安装、使用、拆卸安全技术规程》JGJ196-2010，当多台塔式起重机在同一施工现场交叉作业时，应编制专项方案，并应采取（ ）的安全措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","防倒塌",false,{"key":16,"text":17,"correct":18},"B","防碰撞",true,{"key":20,"text":21,"correct":14},"C","交叉施工",{"key":23,"text":24,"correct":14},"D","人员互用","根据《建筑施工塔式起重机安装、使用、拆卸安全技术规程》JGJ196-2010，当多台塔式起重机在同一施工现场交叉作业时，应编制专项方案，并应采取防碰撞的安全措施。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]