[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1157900,818,1,"单选题","根据《电梯工程施工质量验收规范》GB50310-2002，电梯的电气设备接地支线（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应分别直接接至接地干线接线柱上，不得互相连接后再接地",true,{"key":16,"text":17,"correct":18},"B","可互相连接后再接地",false,{"key":20,"text":21,"correct":18},"C","应可靠接地",{"key":23,"text":24,"correct":18},"D","应设其他安全设施","根据《电梯工程施工质量验收规范》GB50310-2002，电梯的电气设备接地支线应分别直接接至接地干线接线柱上，不得互相连接后再接地。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]