[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1157885,818,1,"单选题","根据《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011，单、双排脚手架拆除作业必须由上而下逐层进行，严禁上下同时作业；连墙件必须随脚手架逐层拆除，严禁（ ）；分段拆除高差大于两步时，应增设连墙件加固。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先拆除整层连墙件再拆脚手架",true,{"key":16,"text":17,"correct":18},"B","先拆脚手架再拆除连墙件",false,{"key":20,"text":21,"correct":18},"C","先拆立杆再拆除水平杆件",{"key":23,"text":24,"correct":18},"D","先拆钢管再拆除扣件","根据《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011，单、双排脚手架拆除作业必须由上而下逐层进行，严禁上下同时作业；连墙件必须随脚手架逐层拆除，严禁先拆除整层连墙件再拆脚手架；分段拆除高差大于两步时，应增设连墙件加固。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]