[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1157878,818,1,"单选题","根据《大体积混凝土施工规范》GB50496--2009，大体积混凝土整体分层连续浇筑或推移式连续浇筑，应缩短间歇时间，并在前层混凝土（ ）将次层混凝土浇筑完毕。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","初凝之后",false,{"key":16,"text":17,"correct":14},"B","终凝之前",{"key":19,"text":20,"correct":21},"C","初凝之前",true,{"key":23,"text":24,"correct":14},"D","终凝之后","根据《大体积混凝土施工规范》GB50496--2009，大体积混凝土整体分层连续浇筑或推移式连续浇筑，应缩短间歇时间，并在前层混凝土初凝之前将次层混凝土浇筑完毕。\\t。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]