[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157858":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1157858,818,1,"单选题","监督检查质量验收的程序是否满足标准的要求，重点检查（ ）的执行情况。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标准体系全部标准",false,{"key":16,"text":17,"correct":14},"B","标准体系中工程质量标准",{"key":19,"text":20,"correct":21},"C","工程建设强制性标准",true,{"key":23,"text":24,"correct":14},"D","工程建设强制性标准和推荐性标准","监督检查质量验收的程序是否满足标准的要求，同时要检查质量验收是否存在遗漏检查项目的情况，重点检查强制性标准的执行情况，填写检查记录表。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]