[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1157829,818,1,"单选题","满足企业和项目管理的要求，并保证工程项目建设活动高效运行。这属于是（ ）评价内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管理标准",true,{"key":16,"text":17,"correct":18},"B","质量标准",false,{"key":20,"text":21,"correct":18},"C","工作标准",{"key":23,"text":24,"correct":18},"D","安全环境卫生标准","管理标准：满足企业和项目管理的要求，并保证工程项目建设活动高效运行。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)专业管理实务 岗位知识","建筑工程",0]