[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157597":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1157597,817,3,"判断题","工程施工前，施工单位应编制检测计划，经建设单位审批后组织实施。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"工程施工前，施工单位应编制检测计划，经监理（建设）单位审批后组织实施。",{"id":6,"name":21,"category":22,"favorite":23},"(标准员)基础知识","建筑工程",0]