[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157573":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1157573,817,3,"判断题","网络计划中，只有-条自始至终全部由关键工作组成的线路叫作关键线路。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"网络计划中，总时差最小的工作称之为关键工作。网络计划中，自始至终全部由关键工作组成的线路或线路上总的工作持续时间（总工期）最长的线路叫关键线路。",{"id":6,"name":21,"category":22,"favorite":23},"(标准员)基础知识","建筑工程",0]