[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157561":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1157561,817,3,"判断题","自由时差是指在不影响紧后工作最迟开始和有关时限的前提下，一项工作可以利用的机动时间。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"自由时差是指在不影响紧后工作最早开始时间和有关时限的前提下，一项工作可以利用的机动时间。。",{"id":6,"name":21,"category":22,"favorite":23},"(标准员)基础知识","建筑工程",0]