[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157249":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157249,817,2,"多选题","某建设工程项目的承包商为了实现项目目标，制订了一系列控制项目目标的主要措施，这些措施的类型有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","管理措施",true,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":14},"C","组织措施",{"key":22,"text":23,"correct":14},"D","经济措施",{"key":25,"text":26,"correct":27},"E","结构措施",false,"ABCD","控制项目目标的主要措施包括：管理措施、技术措施、组织措施、经济措施。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]