[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157245":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157245,817,2,"多选题","施工方进度控制的措施主要包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","法律措施",false,{"key":26,"text":27,"correct":24},"E","行政措施","ABC","施工方进度控制的措施主要包括组织措施、技术措施、经济措施、管理措施。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]