[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157239":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157239,817,2,"多选题","签订合同后，在施工准备阶段必须编制详细的施工组织设计，其主要依据有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标文件和工程量清单",false,{"key":16,"text":17,"correct":18},"B","项目施工质量目标",true,{"key":20,"text":21,"correct":18},"C","项目施工质量计划",{"key":23,"text":24,"correct":18},"D","项目施工程序文件",{"key":26,"text":27,"correct":18},"E","思想、组织、工作保证体系","BCDE","签订合同后，在施工准备阶段必须编制详细的施工组织设计，其主要依据有项目施工质量目标、项目施工质量计划、项目施工程序文件、思想、组织、工作保证体系。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]