[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157236":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157236,817,2,"多选题","运用动态控制原理控制施工进度时，一般的项目控制的周期为一个月，对于重要的项目，控制周期可定为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","一周",true,{"key":16,"text":17,"correct":14},"B","一旬",{"key":19,"text":20,"correct":21},"C","一季",false,{"key":23,"text":24,"correct":21},"D","一年",{"key":26,"text":27,"correct":21},"E","一个项目期","AB","运用动态控制原理控制施工进度时，一般的项目控制的周期为一个月，对于重要的项目，控制周期可定为一周或一旬。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]